Wednesday 30 May 2012

Update & Defects From PCI

Hi all, welcome to another installment of our blog. We had our PCI pre hand over inspection and were suprised with what needs to be fixed up. All that has occured in the last week & a half is the TV & data has been fitted off through the house & the ducted vacuum wall plates have also been fitted off. I have been very displeased with the lack of urgency to get our house completed. I suspect the house will hopefully be done come the end of next week. We also have furniture suppliers hassling us to deliver our good as well. So we are very keen to get the house finished.

Below is the list of defects that require fixing.

  • Bed 1 Door jambs have cracking in wood where the hinges are, Plaster & painting issues throughout, Window seat also needs some extra attention.
  • Ensuite cavity door needs re-staining and sanding rubs on inside wall, framing has cracking and not fixed properly
  • Ensuite needs whole repaint & shower niche trim out of square & poor finish
  • Cabinet Kicker in ensuite is scratched/chipped. Cabinets have paint overspray,
  • Scratchers on shower screens Ensuite & Main Bath
  • Living Room Walls need painting, cornice has dents & a gap in the slab floor between the stud wall (pic below)
  • Window Frame paint cracking
  • Kitchen Meals alfreasco door bow, a wall also has a bow
  • Island bench to a mitre look.
  • Bench & cabinets around oven have paint over spray and are scratched
  • Pantry Door staining runs
  • Laundary cabinet scratches & paint over spray, paint finish
  • Bed 3 Paint issues, Robe slide doors need adjusting. Windows scratched
  • Bathroom niche need re-grouting/sealing, Silicone on shower screens, Vanity draw need re adjusting, power point need re fixing, niche also not square
  • Toilet paint issues
  • Linen Paint issues
  • Bath Tub need re sealing
  • Vanity kick board has silicone overspray
  • Bed2 Paint issues, Hand rail in robe
  • Garage needs repainting ceiling & walls
  • Rear entry door into garage need repainting (paint run lines)
Thats just what was on the simonds list.

There was an independant inspection carried our with another 41 items as well as some items the Site Supervisor didnt write down, which i emailed to our CRC when i sent through the Inspection report.

Robe Doors Fitted

TV & Data Points Fitted Off


Ducted Vacuum Wall Plate

Ducted Vacuum

My Star Serve System (TV & Data point)


Inside The Star Serve Box

Alarm Box In Bedroom Robe

Telephone Point In Our Bedroom

House Alarm Key Pad

Hosue Alarm External Siren

Living Room Showing Gap Along Bottom of the side wall

Close Up of Living Room Gap